Design life
The design life (or design service life) of a building, other structure or component, is the period of use as intended by the designer after which it may need to be replaced. Before this period has elapsed, it should remain fit for purpose.
Design life will vary according to the type and use of the element being considered. BS EN 1990, Eurocode - Basis of structural design, (Eurocode 0) gives indicative design lives for various types of structure:
- Category 1: Temporary structures, not including structures or parts of structures that can be dismantled with a view to being re-used – 10 years.
- Category 2: Replaceable structural parts, e.g. gantry girders, bearings – 10 to 25 years.
- Category 3: Agricultural and similar buildings – 15 to 30 years.
- Category 4: Building structures and other common structures – 50 years.
- Category 5: Monumental building structures, bridges and other civil engineering structures – 100 years.
The design life of some components may be affected by environmental factors such as:
- Moisture, humidity and rain.
- Wind.
- Temperature and temperature fluctuations.
- Pollution.
- Solar radiation.
It may also be affected by considerations such as maintenance practices, intensity of use, and so on.
There is no legally agreed definition of design life (in fact, there is not even a legally agreed definition of 'design'), so if it is to be included in contract documentation as a performance requirement, it is important that it is carefully defined within the contract documents and that it is consistent with all other requirements in the contract documents.
Several other definitions have been developed to quantify the life of buildings, structures and their components, including:
[edit] Related articles on Designing Buildings
- Cradle-to-grave.
- Decommissioning.
- Demolition.
- Economic life.
- End of life potential.
- Fitness for purpose.
- Functional life.
- Life.
- Life cycle.
- Life cycle assessment.
- Obsolescence.
- Permanent structure.
- Re-evaluating the design life of buildings.
- Required life.
- Service life.
- Structures at the end of their design life.
- Technical life.
- Temporary structure.
- Useful life.
- Utilising life cycle costing and life cycle assessment.
- Whole-life costs.
- Whole-life value.
Featured articles and news
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.
Comments